Nam Ngiep 2B Hydropower project is part of Nam Ngiep 2ABC Hydropower project (2A, 2B & 2C). Lao-based Nonghai Group Co. Ltd. is developing several hydropower sites in northern Lao PDR southeast of the Plain of Jars area and another in Kham District. Their website has images of ongoing construction of these sites but very little text in English. Their Facebook page is HERE .

Also see Facebook page with images of construction of these sites created by Lao workers on the projects. These sites have mixed info from other projects and give incomplete details with very little in English - HERE .

Image below shows Nam Ngiep 2B hydropower project construction site at coordinates - 19°09'20.9"N 103°20'46.6"E (19.155809, 103.346280). Also shown is Nam Ngiep 2A site a little downriver.

The engineering, procurement and construction (EPC) contractor for the project was Chongqing Water Turbine Works Co., Ltd (CWTW) from China.

The project installed capacity is 18 MW from 3 Axis Francis turbine-generator sets of 6 MW each with annual output potential of 76 GWh.

The project was finished and commissioned on 31 January 2018 and is currently in operation.

The dam structure is constructed of reinforced concrete with drainage gates.

The project water catchment area is 878 square kilometers.

Non-pressure tunnel of Nam Ngiep 2B HHP was constructed by Zheng Hong Company.

Nam Ngiep 2B site image below:

Images below of Nam Ngiep 2B penstock and plant during construction

Images below of Nam Ngiep 2B plant and switch yard during construction

Images below of dam structure for Nam Ngiep 2B project

Images below of Nam Ngiep 2B powerhouse interior

Nam Ngiep Dams location shown in map below:

Click to see our other web pages for Nam Ngiep 2A and Nam Ngiep 2C.

Satellite image map below for Nam Ngiep 2A, 2B & 2C hydropower projects: